Installation of a multi-fuel boiler at CJSC "International Paper" (former Svetogorsk PPM) for waste biomass utilization and energy generation for own needs, Svetogorsk, Russia*

CJSC "International Paper" (former Svetogorsk PPM)


The project is implemented at CJSC "International Paper" (former Svetogorsk PPM) in Svetogorsk.

The project involves installation of a new multi-fuel boiler and setting up related biomass preparaiton and transportation as well as fly ash handling infrastructure. The boiler will be fired with bark and wood wastes (BWW) and waste water sludge (WWS) that are generated at the Mill. The back up fuel will be natural gas.  The boiler and auxiliary equipment was manufactured and installed by Kvaerner Pulping. Installation of the new boiler made it possible to decommission hot-water PTVM-30 boiler at CHPP-4 and E-75-39-440 steam power boiler at CHPP-3.

The project enables utilization of around 251 kt of BWW and 106 kt of WWS per year to generate heat and electricity. This results in almost complete termination of BWW and WWS dumping and in mitigation of negative environemntal impact. The project also reduces the percentage of fossil fuel in the company's fuel mix.

The project greenhouse gas emission reductions are achieved due to reduction in fossil fuel (natural gas) consumption and due to prevention of anaerobic decay of BWW at dumps.

Expected emission reductions over 2008-2012 – 1.630 Mt ÑÎ2e  

Project status

Validated
24.08.2011
BVC

Project Design Document

Determination Report

  

* The project was developed for ICF/EKO